Ground preparation for a brick-built substation plinth

Liverpool

Sub-base Excavation

Excavation works are underway to reach the formation level, ensuring a stable base for the plinth.

WhatsApp Image 2024-10-10 at 11.21_edite

Shuttering 

Shuttering set in place to define the plinth dimensions and hold the concrete during the pour.

WhatsApp Image 2024-10-10 at 11.22.08.jpeg

Brickwork Build Phase 1

Initial brickwork courses laid to establish the substation plinth’s base. Each course is set to precise tolerances, ensuring alignment with the structural design and providing a solid foundation for subsequent construction phases.

WhatsApp Image 2024-10-10 at 11.13.24.jpeg

Steel work Installation

Steelwork is fixed in place to support the substation framework. Installed to precise alignment, this phase ensures structural integrity and ties in with the earthing system for safety compliance.

WhatsApp Image 2024-11-04 at 10.36_edited.jpg

Concrete Blinding

A layer of concrete blinding is laid over the compacted sub-base. This creates a clean, level surface for setting out the plinth and protects reinforcement from direct contact with the ground

WhatsApp Image 2024-10-10 at 11.21_edite

Concrete Base Plinth

The concrete base of the plinth was poured and levelled. This forms the main structural platform to support the substation, built to specification for strength and durability.

WhatsApp Image 2024-10-10 at 11.22_edited.jpg

Type 1 MOT Compaction

Type 1 MOT laid and compacted in layers to create a stable and well-drained base. Proper compaction is critical at this stage to prevent future settlement and ensure long-term durability of the plinth structure.

WhatsApp Image 2024-11-04 at 10_edited.j

Top Base-Plinth

The final concrete layer was poured to complete the top of the plinth. This forms a smooth, level surface ready for equipment installation and ensures the structure meets final height and finish specifications.