Client: Tier 1 Multi-Utility Contractor Location: Preston, Lancashire Duration: 12 Weeks Services Delivered: EV-ready substation installation 1.3km of excavation and reinstatement HV cable pull from the substation to the new housing development Traffic management Footway, carriageway, and grass verge works Environmental and ecological controls Stakeholder engagement and resident liaison Project Overview: Excavate & Reinstate Ltd was contracted to deliver key infrastructure supporting the future of electric vehicle charging. This long-term project formed part of a wider development, providing a high-voltage connection between a new substation and the housing estate’s point of connection (POC). Scope of Works: EV-ready substation base and civils Full HV cable pull from substation to POC 1.3km of trenching and reinstatement Works across grass verges, footways, and the carriageway Traffic management and safe public access at all stages Ongoing communication with residents to minimise disruption Collaboration with multiple utility contractors Wildlife protection during an ecological interruption Compliance & Safety: All works were completed in full compliance with: Street Works Regulations ISO standards EUSR requirements We operated under strict permit conditions, limited to 250m intervals. This required phased planning and careful coordination to keep the public safe while maintaining access at all times. Challenges & Solutions: During the project, an unexpected ecological interruption required the temporary halting of works. We followed all wildlife protection procedures and resumed without delay once cleared. Coordination with other contractors was key. Our team worked closely with gas, water, and telecoms providers to avoid clashes and keep the programme on track. Outcome: Delivered on time, within scope, and without compromise. The client praised our professional delivery, collaborative approach, and ability to work under tight permit constraints. The new infrastructure now supports EV expansion across the site, forming a critical part of the area’s long-term energy strategy. Key Stats: 1.3km total excavation Full HV cable route installed 12-week programme Zero safety incidents Fully EV-ready infrastructure delivered